|
Locomotive A39 was built for Coras Iompair Éireann (CIE), the
Irish State owned transport company by Metropolitan Vickers at
their premises at Dukinfield, Manchester, in 1955. A39 was part
of a class of 60 Co-Co locomotives, designated “A” class and
numbered A1 – A60 inclusive, which were ordered as part of the
drive to eliminate the majority of steam traction from the
railways of the Irish Republic in the late 1950s. The contract
to build these locomotives was signed at Heuston Station,
Dublin, on 5th May 1954. The sixty “A” class locomotives
were assembled by Metropolitan Vickers at their premises at
Dukinfield, Manchester, between 1954 and 1955. Metropolitan
Cammell Carriage & Wagon Co Ltd. constructed the body shells at
Birmingham, the English Steel Corporation constructed the bogies
in Sheffield, and Crossley Brothers at Openshaw, Manchester,
supplied the engines. The electrical equipment for these
locomotives was provided by Metropolitan Vickers Electrical Co.
Ltd.
A39 eventually entered traffic with CIE on 14th May 1956. When
built, these locomotives were originally fitted with a Crossley
HSTV8 engine of 1200 hp. However, the Crossley engines proved to
be extremely troublesome and unreliable. In 1968, the decision
was taken to re-engine the whole class with General Motors
12-645E engines of 1325 hp. A39 itself was re-engined on 23rd
July 1969, and subsequently re-numbered A39R. Eventually, the
letter classification system was dropped by CIE, and the
locomotive was renumbered to 039.
In early 1994, the Irish Traction Group were asked by Iarnród
Éireann to nominate three 001 (A) class locomotives for possible
preservation by the Group. The three locomotives selected by the
Group as being in the best condition at the time were 001, 003
and 039. Locomotive 001 was subsequently ruled out as it
suffered a cracked fuel tank, which left 003 and 039 as the two
locomotives to be preserved by the Group. 039 was selected by
virtue of the fact that it had the most recently overhauled
engine fitted, and had received a rewire and body overhaul in
March 1990.
Locomotive 039 was eventually taken out of traffic by Iarnród
Éireann on 14th March 1995 with a bogie defect. Its last working
was to haul a defective ex-BR steam van from Mallow to
Inchicore. However, unlike the other withdrawn “A” class
locomotives, 039 was not added to the scrap line at Inchicore,
but was locked away in secure storage in Diesel No. 2 Shop. The
last “A” class locomotive in traffic was 003 and this was taken
out of service on 5th April 1995, after 40 years in service.
During early May 1995, 039 was taken into Diesel No. 1 Shop at
Inchicore to receive a replacement bogie to return it to full
working order, and was later noted in the Main Running Shed on
13th May 1995 receiving an “AB” exam. Following this work, 039
was then moved back into secure storage in Diesel No. 2 Shop. In
August 1995 Iarnród Éireann announced its intention to run a
farewell to the “A” class locomotives on Saturday 23rd September
1995 using 039. In early September the locomotive was repainted
back into its original silver livery and renumbered A39.
Following its use on this railtour, A39 was locked away in
Diesel No. 2 Shop once again pending eventual sale to the ITG,
which eventually took place on 13th November 1995. A39 then
remained at Inchicore Works, being started up occasionally to
keep everything in working order. At this point the ITG was
attempting to arrange its own insurance for main line running,
but it was proving difficult to find a broker willing to provide
the necessary cover.
In September 1997, the ITG received an approach to use A39 for a
filming contract in connection with a joint RTE/BBC drama called
“Amongst Women”. Filming was to take place at Castlerea Station,
Co. Roscommon, and would involve A39 working under its own power
on the main line for the first time in preservation, hauling a
rake of RPSI coaches in the station area. The locomotive was to
be covered by the RPSI’s insurance for this contract, as the ITG
had still not been able to arrange its own main line running
insurance at this time. On Wednesday 15th October 1997, A39 left
Inchicore Works for the first time in over two years when it was
hauled to Westport along with a rake of RPSI coaches for
stabling, prior to being hauled back to Castlerea the following
day for the start of filming.
Following its arrival at Westport, it was decided to take A39 on
a light engine test run out towards Castlebar, as there had been
no chance to test the locomotive “on the open road” previously.
However, A39 suffered an electrical fault around 3 miles out,
and was unable to take power. Iarnród Éireann had to send a
light engine from Westport to haul A39 back to the town. Despite
working long into the night, the fault could not be rectified.
The following morning, A39 and the RPSI coaches were hauled back
to Castlerea ready for filming to start. At this point it was
intended to put A39 on the front of the train and propel the
train backwards and forwards using the Iarnród Éireann
locomotive hidden away at the back of the train. Fortunately,
the early filming only required shots of the inside of the
train, and also general station scenes, which did not require
A39 to be used, so this gave the ITG fitters more time to try to
trace the fault. After a few telephone calls to Inchicore the
fault was eventually diagnosed, and a temporary repair
undertaken to enable the locomotive to work under its own power
once again. Over the next two days, A39 worked several movements
in and out of the station, culminating in a final run out
approximately five miles towards Roscommon, when the locomotive
managed to reach approximately 50 miles an hour. Following the
filming, A39 and the RPSI coaches were hauled back to Inchicore.
Towards the end of 1998, the ITG finally managed to obtain the
necessary insurance cover to start main line running. At
approximately 12:15 on Friday 18th December 1998, A39 set off on
a light engine test run from Inchicore Works to Sallins and
back. A second test run took place on 21st January 1999,
followed by its first passenger working two days later on 23rd
January 1999, when it operated the “Silver Cloud” railtour from
Dublin to Waterford, Waterford to Rosslare Europort and back
from Rosslare Europort to Dublin. Over the next twelve months
A39 operated four railtours, these being:
23rd January 1999
Silver Cloud Railtour
27th March 1999
Back in Black Railtour
12th June 1999
Mayo Metro-Vick Railtour
9th October 1999
Leitrim Leprechaun Railtour
Although these railtours just managed to successfully re-coup
the hefty insurance costs, falling passenger numbers meant that
it could not be sustained for a second year. The decision was
taken to suspend main line running for an indefinite period
until it was deemed financially viable once again. However, as
we still had around two months worth of insurance cover left, it
was decided to run a final “mini-railtour” in connection with
the Group’s 10th Annual General Meeting which was being held at
Inchicore Works on Saturday 13th November 1999. This railtour
was only open to those members who attended the AGM, and invited
guests. The railtour ran from Dublin Heuston to Wicklow and
back, and was formed of a short rake of RPSI coaches. Following
the railtour, A39 returned to store at Inchicore Works, where it
has remained ever since.
Between November 1999 and mid-2001 the locomotive was started
periodically to keep it fully operational. In 2001 the Group was
approached by contractors engaged to undertake track relaying
work on Northern Ireland Railways with a view to hiring the
locomotive to haul track relaying trains. The locomotive was
made ready to be moved north, but the deal fell through at the
last minute. It was then decided to “mothball” the locomotive
until such time that future work could be found or the insurance
issue was resolved.
During the intervening period, the engine room was gradually
cleaned out and repainted. In 2006 it was decided to make a
start on returning the locomotive to working order once again.
However, by this time the external appearance of the locomotive
was starting to look a bit tatty, and so it was decided in 2007
to completely repaint the outside of the locomotive as well into
CIE black livery. In addition, a considerable amount of
mechanical and electrical work was also carried out in 2007 to
prepare the locomotive’s engine for starting.
In early January 2008 a set of replacement batteries were
obtained and fitted into locomotive A39. On Tuesday 8th January
2008, the batteries were connected together and an attempt made
to start the engine, and at around 10:20 A39’s engine burst into
life for the first time in six years. The only immediate problem
discovered on starting the engine was that one of the hooter
buttons was stuck, and as the control air pressure built up, the
hooter started to sound. This was immediately rectified, and a
start was then made on checking some of the locomotive’s
auxiliary equipment.
Over the following few weeks, most of the auxiliary equipment
was tested including the windscreen wipers, cab heaters, foot
heaters, headlights, marker lights, hotplate, and cab lights.
Oil levels in the engine, compressor, exhauster and governor
were all checked and were found to be full. A brake test was
undertaken, and although the vacuum was a bit low at 18 inches
(the correct reading being 21 inches), the brakes operated
correctly. Each of the four power controllers were checked in
turn, and the locomotive took power each time. The train radio
was checked and found to be working correctly, but this was in
need of replacement anyway with the new type. The fitting of the
new radio equipment was eventually completed on Saturday 23rd
February 2008.
The locomotive is now fully operational, and is being regularly
started to keep the batteries fully charged.
|

A39 under
construction at Metropolitan Cammell Works in Birmingham.
Metropolitan Cammell
Archive

A39 (as
A39R) at Ballinasloe 25 May 1975
Jonathan
Allen

039 under repair at Inchicore Works while
still in service with Irish Rail
23 October 1993. Derek Thompson


A39 at Castlerea. Peter Jones.

A39 undergoing body restoration at Inchicore
17 February 2007

A39 nearing completion at Inchicore 02 June 2007

A39 following repaint on 22 December 2007

A39's engine room following repainting 13
December 2008 |